Form 4 and notifiable work: what your plumber must lodge

Notifiable work is plumbing and drainage work in an existing building that can be done without a council permit or mandatory inspection. The plumber or drainer must register it with QBCC on a Form 4 within 10 business days of issuing the invoice, and must give a copy to the owner or to whoever engaged them.

What falls into the category

QBCC's examples are additions, extensions or renovations to kitchens and bathrooms, installing or replacing water heaters (electric, gas, solar or heat pump), and installing new or relocating fixtures such as toilets, showers, basins and kitchen sinks. There are 12 categories in all, set out in schedule 1 of the Plumbing and Drainage Regulation 2019.

New construction is different. QBCC states that plumbing and drainage work associated with new construction is permit work, which goes through the council with inspections at set stages.

The four kinds of plumbing work

How Queensland sorts plumbing and drainage work, from QBCC's home owner guide and notifiable work pages
KindTypical jobPaperwork
Permit workPlumbing for a new houseCouncil permit and staged inspections, ending in a compliance certificate from the plumbing inspector
Notifiable workBathroom renovation, replacement water heaterForm 4 lodged with QBCC by the licensee
Minor workSorted job by job on QBCC's "Permit, minor or notifiable work?" pageNo Form 4
Unregulated workReplacing a tap washer or a shower headNone, and no licence needed

The deadline, precisely

QBCC's notifiable work page says the work must be registered within 10 business days of issuing an invoice for the work. If no invoice is issued, for example a plumber working on their own home, it must be registered when the work becomes operational. QBCC's home owner guide words it as within 10 business days after the notifiable work is finished. On a normal paid job the two readings land close together, since the invoice follows completion.

Form 4 is for private persons and businesses. Form 4a is the public sector version.

What the form says and who pays

A Form 4 records who performed the work, what was done and the address. The licensed contractor is responsible for submitting it and paying the fee to QBCC. The guide adds that the contractor may pass the cost of lodging, including any administrative costs, on to the property owner. So a small "Form 4" line on a hot water invoice is legitimate, and you are entitled to the copy that goes with it.

Checking that it was done

QBCC runs a public search of the notifiable work register by address. It is worth a minute after any bathroom renovation, and again when you buy a house with a newish hot water unit. If a form should exist and does not, QBCC's advice to home owners is that you can lodge a complaint.

Lodging does not mean the job is exempt from scrutiny. QBCC and local governments carry out routine audits of notifiable work, and the guide says a council that decides to audit will contact the home owner for permission to enter and inspect.

Short answers

Who lodges the Form 4, me or the plumber?

The plumber or drainer. QBCC says licensees are required to register notifiable work and must also give a copy to the owner or to the person who engaged them.

Is replacing a hot water system notifiable work?

Yes. Installing or replacing a water heater, whether electric, gas, solar or heat pump, is one of QBCC's listed examples.

A builder hired the plumber for my extension. Do I get the form?

The copy may go to the builder as the party who engaged the plumber. QBCC's guide says the owner of a property where notifiable work was performed may contact QBCC to access a copy.

Sources

Written by the Plumber & Gasfitter editorial desk from the sources listed, all read in November 2026. This is general information for Queensland and not legal advice. Rules change; the linked regulator pages are the authority.