Defective plumbing or gas work: how a QBCC complaint works
First give the contractor written notice of each defect with a deadline to fix it; QBCC's example is 14 days. If that fails, lodge a complaint with QBCC. Plumbing, drainage and gas fitting complaints are accepted at any contract value. For non-structural defects the complaint must be lodged no later than 12 months from completion of the work.
Before you lodge
QBCC expects owners to try to resolve the matter directly. Its defective work page sets out the groundwork:
- Speak to your principal contractor and clearly identify your concerns.
- Give written notice listing each defective or unfinished item, with a timeframe to rectify.
- Give the contractor reasonable access to the site to do the repairs, and follow any dispute steps written into your contract.
- Check the contractor's licence on the QBCC licensee register. If they do not hold the correct licence, the rectification has to be done by a suitably licensed contractor.
Keep the notice simple and dated. A numbered list with photographs is better than a long email.
No minimum job size for plumbing
For most building work QBCC will only act where the contract value, including labour, materials and GST, is more than $3,300. That threshold does not apply to plumbing, drainage or gas fitting, which qualify at any value. Fire protection and building design are on the same exempt list, and hydraulic design work has its own lower threshold of more than $1,100.
The clocks
| Situation | Limit |
|---|---|
| Non-structural defect | Lodge no later than 12 months from completion of the work |
| Structural defect | Lodge within 12 months of noticing the defect |
| QBCC issuing a direction to rectify | QBCC has 6 years and 6 months from when the building work was completed |
A leaking shower that shows up fourteen months after a bathroom renovation is the classic case where the first limit bites. Do not sit on a defect while you negotiate.
What QBCC can do
If the contract has ended, QBCC may inspect the disputed work and, where required, issue the contractor with a direction to rectify. The page says a direction typically gives the contractor 35 days to fix the work, and that it will appear on the contractor's public licence history. That last consequence is the real lever, since future customers who check the register will see it.
What QBCC cannot do
QBCC lists its limits frankly. It cannot require payment or refunds, make decisions about your contract, supervise the repairs or fix the work itself. Money disputes belong elsewhere.
Plumbing has its own form
QBCC's advice to home owners is to use its online plumbing and drainage complaint form for plumbing issues and the general complaints form for contract concerns. You can complain if you believe work was unlicensed, defective or non-compliant, or if you never received a Form 4 for notifiable work. Local governments also have a role: QBCC's guide says you can ask the council to inspect plumbing work you believe is defective, and warns that councils can charge for re-inspection.
Gas safety is handled by a different regulator. The Queensland Government's gas safety page gives gassafe@rshq.qld.gov.au for gas safety questions and complaints.
Short answers
My plumbing job cost less than $3,300. Can QBCC still help?
Yes. QBCC says the $3,300 threshold does not apply to plumbing, drainage or gas fitting work.
Will QBCC make the plumber refund me?
No. QBCC states it cannot require payment or refunds. Its main power is a direction to rectify the work.
How long does a contractor get to comply with a direction to rectify?
QBCC says a direction typically gives the contractor 35 days.
Sources
- QBCC: Help with defective work
- QBCC: Plumbing problems? Here's what Queensland home owners need to know
- QBCC: Home Owner's Guide to Plumbing Matters, May 2025 (PDF)
- Queensland Government: Using natural gas and LPG safely
Written by the Plumber & Gasfitter editorial desk from the sources listed, all read in November 2026. This is general information for Queensland and not legal advice. Rules change; the linked regulator pages are the authority.